LSC, GPU Energy
and ASCI

SolarScapes Commission

 

Budget and donations: Donations to offset equipment and labor costs are best negotiated once the commission is awarded. However, we expect about half of this budget will be offset by favorable leases or donations-in-kind.

Preliminary Budget (pre-donations)

  

Light systems (4 Intellabeams)

$25k

Personal Computer to control lights

$2k

Light Controller Interface

$1k

Power Cabling   

$1k

Projection screens (4)

$6k

Rigging   

$3k

Spare lamps (24 for 2 years)

$5k

Labor to install screens  

$2k

Labor to install lighting system

$2k

Misc.(insurance, hardware, etc)

$3k

Total     

$50k

 

copyright Greg Blonder 1999